Table of Contents

Contents of Section:
Data Segment List 

Electronic Commerce / Implementation Guide / Chapter 3
3.4 Production Reporting (Buildup) (Order Status Report) 870
Processor to Dofasco

This transaction set is the ANSI ASC X.12 Version 3030 equivalent of the AISI/COMPORD 
Production Reporting transaction in the AISI Outside Processing System (transaction code 
92) 

Purpose:

The Production Reporting transaction provides the format and establishes the data content
of a Dofasco order status report for reporting production for use in an electronic business 
environment. 

Application

The Production Reporting transaction is used to report the production cycle progress to 
Dofasco.  Dofasco requires the Processor to adhere to the following reporting practices: 

    1) The 'discharge' weights, including scrap, must reconcile to the 'charged-in' 
        weight of an item
Note: Off cut items banded together and mixed coil ID's in bundles must first be reported 
to reconcile each coil ID's weight.  Then a 'buildup' transaction must be sent via EDI to 
indicate which coil ID's were combined. 
    2) The Dofasco lift ticket number must be sent in the EDI transmission 
    3) For slit cut items: 
      a) each slit cut must be assigned a unique item ID by the processor 
      b) the Dofasco lift ticket number(s) attached to the lift must be sent in 
          the EDI transmission 
    4) Material Damage Fault (AISI Table 72) and Type (AISI Table 73) can 
        be provided with the 'discharge' coil ID, if applicable 
    5) Production Unit (AISI Table 76) must be reported 
    6) Multiple processes processed on a single production unit must be reported 
    7) Next Process (AISI Table 66) must be reported including any unscheduled 
        next process 
    8) A packaging process performed 'off line' must be reported 
    9) The following method must be used for reporting production when a master
        coil     is processed for more than one Dofasco customer sales order number: 
      a) report production for the portion of the master coil produced 
          on the original Dofasco customer sales order number 
      b) report process code 52 (unfinished-AISI Table 66) for 
          the remainder of the coil to leave this piece ahead of the process 
      c) a Reapplication (867 Product Transfer & Resale) must then be sent 
          to reapply the unfinished piece to the next Dofasco customer sales 
          order number 
      d) report production in the same manner as a), b), c) above until the 
          coil is consumed 
This transaction will be electronically received by Dofasco from any of its Outside Processors/Outside 
Storage Facilities capable of X12 EDI communications. 

Components of Data Segment List
Header Transaction Sets
 
Production Reporting Example 
 
Number: OP-7998-007
Issue Date: October 1, 1995
Revision Date: January 29, 1997

3.4.1 Data Segment List

Tables Seg 
ID 
Segment Name ANSI 
Reqmt 
Dofasco 
 Reqmt 
Max 
 Use 
Loop ID, 
No of Repeats
Table 1 Header Information ST 
BSR 
N1
DTM
Transaction Set Header
Beginning Segment for Order Status Report
Name
Date/Time Reference

M
O
O

M
M
M

1
1
1
N1/2
Table 2 Order Hierarchical Level  HL 
PRF 
Hierarchical Level 
Purchase Order Reference



HL/1000 
Table 3 Component Hierarchical Level HL 
REF 
DTM 
PO1 
PID 
MEA 
ISR 
PID
Hierarchical Level
Reference Numbers
Date/Time Reference
Purchase Order Baseline Item Data
Product/Item Description
Measurements
Item/Status Report
Product/Item Description







O







O




15 
40 

HL/1000 
 
 
 
 

ISR/5 
 

Table 4 Item Hierarchical Level  HL 
REF 
DTM 
PO1 
PID 
MEA
Hierarchical Level
Reference Numbers
Date/Time Reference
Purchase Order Baseline Item Data
Product/Item Description 
Measurements





O
M




M




10 
40 
HL/1000
Table 5 Summary Information CTT 
SE 
Transaction Totals 
Transaction Set Trailer 




top of page | Table of Contents